High Coast Bridge, Sweden
Project Period: 2005 + 2025
Scope of works - 2005:
Design & Installation of new dehumidification system for main cables & box girder
Installation of CableGuard Elastomeric Wrap System
Access Facilities.
Scope of works - 2025:
Design & Installation of new dehumidification system for main cables & box girder
New & improved SCADA System (Siemens)
Installation of further injection & exhaust sleeves & changing of existing.
Access Facilities.
Minor repairs on surface treatments.
Client: Trafikverket (Swedish Public Roads Administration)